October 4, 2026
Building Plan Revision · BLD-25-0514691-REV3 · PENDING
Arch has revision 2 changes which were unreleased. They were combined and are part of
this revision 3 submittal.
Electrical, Mechanical, and Plumbing had revision 2 changes, and revision 3 changes
which are separated. All changes are shown in the attached revision 3 sets.
Structural has revision...
September 30, 2026
Commercial Miscellaneous Permit · BLD-26-0528434 · PENDING
New Fire Alarm Installation.
September 28, 2026
Commercial Miscellaneous Permit · 26TMP-101010 · OTHER
August 27, 2026
Building Plan Revision · BLD-25-0514691-REV2 · PENDING
This revision is to further build out the vanilla shell so that potential new tenants can complete their build out quicker.