October 5, 2026
Commercial - Fire Sprinkler · BP-202604047 · PENDING
9TH FLOOR SPEC SUITE (SUITE 900, 910, 950, & 970) -- CENTURY TO ADD AND RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM PER NFPA 13.
October 5, 2026
Commercial - Low Voltage · BE-202606995 · ISSUED
MIDTOWN PLAZA 9TH FLOOR ALARM -- AFPS SHALL PROVDE AND INSTALL NEW NAC DEVICES IN RENOVATED SUITE PER SYSTEM DRAWING.
October 5, 2026
Commercial - Low Voltage · BE-202606994 · ISSUED
MIDTOWN PLAZA 12TH FLOOR ALARM -- AFPS SHALL PROVIDE AND INSTALL NEW NAC DEVICES IN RENOVATED SUITE PER SYSTEM DRAWING
September 24, 2026
Commercial Alteration · BB-202608390 · PENDING
1ST FLOOR INTERIOR DEMOLITION (COM) (CC) -- SCOPE OF WORK ON 1ST FLOOR IN SECOND GENERATION SUITE AREAS TO INCLUDE DEMOLITION ONLY FOR PARTIAL FLOOR SUITES THAT ARE VACANT. EXISTING
EGRESS EXITS AND CORRIDOR DEMISING PARTITIONS TO REMAIN TO CONTAIN DEMOLITION AREAS FROM REMAINING LOBBY ENTRY, RES...
Cost of construction: $35,000
September 9, 2026
Commercial - Plumbing · BP-202603668 · ISSUED
Pace Management / Suite 920 / PO#26-439 -- Insall 1 sink, install 1 water heater
September 9, 2026
Commercial - HVAC · BM-202604445 · ISSUED
Pace Management / Suite 920 / PO#26-439 -- New low pressure duct, new/relocated supply and return grills, insulation
September 2, 2026
Commercial - Low Voltage · BE-202606197 · ISSUED
PACE MANAGEMENT STE 920 ALARM -- AFPS SHALL PROVIDE AND INSTALL NEW NAC DEVICES IN STE 920 AS INDICATED ON THE SYSTEM DRAWING.
September 2, 2026
Commercial - Low Voltage · BE-202606181 · ISSUED
Low Voltage Suite 920 -- Data Outlets Ste 920 Install
September 1, 2026
Commercial Miscellaneous · 26TMP-057745 · OTHER
Low Voltage Suite 920 -- Install Data outlets
September 1, 2026
Commercial Alteration · 26TMP-057736 · OTHER
August 31, 2026
Commercial - Electrical · BE-202606075 · ISSUED
Pace Management Suite 920 -- Add (4) duplex, add power for insta hot, add (2) dedicated GFCI's, relocate (7) 2x4's, add wall sensor, add power for flood stop, add wall sensor, add switch
August 12, 2026
Commercial - Fire Sprinkler · BP-202603183 · PENDING
PACE MANAGEMENT (SUITE # 920) -- CENTURY TO ADD AND RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM PER NFPA 13.
August 12, 2026
Commercial Alteration · BB-202607053 · PENDING
Pace Management Suite 920 (LC)(CO) -- INTERIOR ALTERATION OF EXISTING BUSINESS OFFICE. EXISTING OFFICE SUITE IS VACANT. NO ALTERATION TO EXISTING TENANT DEMISING WALLS. WORK INCLUDES SELECTIVE DEMOLITION, CONSTRUCTION OF NEW PARTITIONS, NEWDECORATIVE FINISHES, EXISTING CEILING AND GRID TO REMAIN,...
Cost of construction: $67,884
August 4, 2026
Commercial Alteration · BB-202606758 · PENDING
9th Floor Spec Suites -- Interior buildout of an existing business suite in an existing building to create a spec suites. Extent of work to include new walls, door and interior finishes. Modification to MEP systems as requires. The Suites are to remain vacant until leased which a certificate of o...
Cost of construction: $1,125,825
July 2, 2026
Commercial - Low Voltage · BE-202604591 · ISSUED
Prolific Banking – Suite 750 -- Installation of low-voltage systems including Cat6A data cabling, access control, CCTV cameras, audiovisual cabling, and network equipment for tenant build-out in Suite 750.