October 1, 2026
Commercial Alteration · BB-202608569 · PENDING
PIEDMONT ATLANTA HOSPITAL BUILDING 105 LEVELS 3 & 4 (COM) (CO) -- PROJECT SUMMARY: THE PRIMARY OBJECTIVE IS TO ESTABLISH A GME PROGRAM FOR THE PIEDMONT ATLANTA CAMPUS. THIS WILL CONSIST OF THE RENOVATION OF THE 3RD AND 4TH FLOOR OF THE 105 BUILDING ON THE PIEDMONT ATLANTA CAMPUS. THE SPACES WILL...
Cost of construction: $3,200,000
October 1, 2026
Commercial Alteration · BB-202608567 · PENDING
PIEDMONT ATLANTA HOSPITAL BUILDING 35 (LC) -- PROJECT SUMMARY: THE PRIMARY OBJECTIVE IS TO ESTABLISH A GME PROGRAM FOR THE PIEDMONT ATLANTA CAMPUS. THIS WILL CONSIST OF THE RENOVATION OF THE LEVEL L FLOOR OF THE 35 BUILDING ON THE PIEDMONT ATLANTA CAMPUS. THE SPACES WILL INCLUDE PREFUNCTION WAITI...
Cost of construction: $1,200,000
September 24, 2026
Commercial - Electrical · BE-202606725 · ISSUED
PAH Pharmacy Expansion Ground Floor -- Interior renovation to an existing space
September 23, 2026
Commercial - Low Voltage · BE-202606694 · ISSUED
PHARMACY EXPANSION / GROUND FLOOR -- INSTALLATION OF STRUCTURED CABLING
September 22, 2026
Commercial Alteration · BB-202608292 · PENDING
Piedmont Atlanta Hospital - Outpatient Diagnostic Center Ground Floor CV CT Renov (COM) (CC) -- THE PROJECT IS A RENOVATION OF A 982 SQ.FT. EXISTING CT IMAGING ROOM ON GROUND LEVEL OF AN EXISTING MEDICAL OFFICE BUILDING. THE
PROJECT INCLUDES BUILDING TWO NEW PREP ROOMS, A WAITING ROOM AND A RENOV...
Cost of construction: $700,000
September 21, 2026
Commercial - Low Voltage · BE-202606610 · PENDING
PHARMACY EXPANSION / GROUND FLOOR -- MODIFICATION TO FIRE ALARM SYSTEM FOR RENOVATION.
September 16, 2026
Commercial Alteration · BB-202608100 · PENDING
EHC PIEDMONT ATLANTA HIH 10 BED EXPANSION PART C -- Part C - Added Bathroom, Added Office and Storage Renovation in existing elevator Lobby and
storage space.
Cost of construction: $300,000
September 16, 2026
Commercial Alteration · BB-202608099 · PENDING
EHC PIEDMONT ATLANTA GA HIH 10 BED EXPANSION PART B -- Part B - Office to Patient Room Renovation
Cost of construction: $1,200,000
September 16, 2026
Commercial Alteration · BB-202608098 · PENDING
EHC PIEDMONT ATLANTA GA HIH 10 BED EXPANSION PART A (LC) (CC) -- PART A –ADMINISTRATION / SUPPORT AREA
THE SCOPE OF WORK CONSIST OF THE PARTIAL INTERIOR RENOVATION OF EXISTING 6TH
FLOOR ADMINISTRATIVE AND SUPPORT AREAS. WORK INCLUDES SELECTED DEMOLITION AND
RENOVATION OF EXISTING OFFICES, ADMIN...
Cost of construction: $800,000
September 3, 2026
Commercial - Low Voltage · BE-202606255 · ISSUED
PAH Legacy OR -- Renovating existing fire alarm system, fit out to replace office space with OR rooms
September 3, 2026
Commercial - Low Voltage · 26TMP-057242 · OTHER
PAH Legacy OR -- Renovating existing fire alarm system, fit out to replace office space with OR rooms
August 27, 2026
Commercial - Low Voltage · BE-202606025 · ISSUED
PIEDMONT ATLANTA HOSPITAL PATHOLOGY RENOVATION -- MODIFICATION TO FIRE ALARM SYSTEM FOR RENOVATION.
August 25, 2026
Commercial - Low Voltage · BE-202605915 · ISSUED
MT Prep/Post -- Renovation of Fire Alarm system in existing Future Use/Tenant spaces for fit out of Preparation/Post work spaces.
August 25, 2026
Commercial - Low Voltage · BE-202605913 · ISSUED
Piedmont Atlanta Hospital - Project 158 10th Floor -- Alteration of the existing fire alarm system. Renovating the 10th floor of the Marcus Tower to patient fit out.
August 25, 2026
Commercial - Low Voltage · BE-202605911 · ISSUED
Piedmont Atlanta Hospital - Project 158 5th Floor -- Alteration of the existing Fire Alarm System. Renovating part of the 5th floor of the Marcus Tower for patient fit out
August 25, 2026
Commercial - Low Voltage · BE-202605910 · ISSUED
Piedmont Atlanta Hospital - Project 158 4th Floor -- Alteration of existing Fire Alarm System. Renovating existing shell space into patient unit fit out of 4th floor of the Marcus Tower
August 20, 2026
Commercial Alteration · BB-202607319 · PENDING
Pharmacy Expansion / Ground Floor -- INTERIOR MODIFICATION OF EXISTING RESPIRATORY THERAPY OFFICE SUITE FOR NEW PHARMACY CONFERENCE ROOM AND OFFICES. INTERIOR MODIFICATION OF EXISTING PHARMACY OFFICE FOR AUTOMATED MEDICATION DISPENSING CAROUSEL.
Cost of construction: $685,000
August 17, 2026
Commercial - Low Voltage · 26TMP-053649 · OTHER
Piedmont Atlanta Hospital - Project 158 10th Floor -- Alteration of the existing fire alarm system. Renovating the 10th floor of the Marcus Tower to patient fit out.
August 17, 2026
Commercial - Low Voltage · 26TMP-053646 · OTHER
Piedmont Atlanta Hospital - Project 158 5th Floor -- Alteration of the existing Fire Alarm System. Renovating part of the 5th floor of the Marcus Tower for patient fit out
August 17, 2026
Commercial - Low Voltage · 26TMP-053644 · OTHER
Piedmont Atlanta Hospital - Project 158 4th Floor -- Alteration of existing Fire Alarm System. Renovating existing shell space into patient unit fit out of 4th floor of the Marcus Tower
August 6, 2026
Commercial - HVAC · BM-202603722 · ISSUED
Piedmont Atlanta Hospital - LINAC Replacement -- Mechanical scope for the replacement of a LINAC unit. This involves installation of a new FCU, a Heat Exchanger, and the associated piping/insulation/duct rework
August 5, 2026
Commercial - Low Voltage · BE-202605391 · ISSUED
Piedmont Radiation Oncology Low Voltage 26821 -- Installation of data cabling for remodel
August 5, 2026
Commercial - Electrical · BE-202605390 · ISSUED
Piedmont Radiation Oncology Electrical 26821 -- Installation of data cabling for remodel
August 3, 2026
Impact Fees - Fees · 26-0263 · OTHER
PIEDMONT ATLANTA HOSPITAL-WOMENS SERVICES RENOVATION-IMPACT FEES -- THE PROJECT CONSISTS OF THE RENOVATION OF AN EXISTING FAMILY
LOUNGE SPACE AND AN APPROXIMATE 400 SQUARE FOOT BUILDING EXPANSION OF SECOND FLOOR OVER THE CANOPY, ENLARGING THE LOUNGE AREA. **PER DESIGN PROFESSIONAL, THE 400 SF BU...
Cost of construction: $2,000,000
July 26, 2026
Commercial Alteration · BB-202606482 · PENDING
Pharmacy Expansion Phase 2 (Ground Floor) (LC) -- PHASE 2: INTERIOR MODIFICATION OF EXISTING PHARMACY OFFICES FOR NEW BULK STORAGE, MEDICATION REFRIGERATORS AND AUTOMATED MEDICATION DISPENSING CAROUSEL.
Cost of construction: $50,000