← Back to leads

Owner: PIEDMONT HOSPITAL INC

3 properties on file · type on file: corp
Matched by exact owner name -- name-formatting variations (e.g. a different combination of joint owners, or a missing middle initial) won't be linked together automatically.

35 COLLIER RD NW, Atlanta 30309

2026-07-14
BE-202604821 · ELECTRICAL · ISSUED
RESPIRATORY THERAPY / SUITE M200 -- MODIFICATION TO FIRE ALARM SYSTEMS FOR RENOVATIONS.

2001 PEACHTREE RD NE, Atlanta 30309

2026-07-06
BB-202606023 · BUILDING · PENDING
Piedmont Physicians Group - Head & Neck Clinic (Suite 610) CO -- Interior renovation of a vacant second generation tenant space on the 6th floor of the Piedmont Atlanta Hospital 2001 professional office building for a new medical office suite.

1968 PEACHTREE RD NW, Atlanta 30309

2026-07-23
BP-202602943 · FIRE · PENDING
PIEDMONT TRANSPLANT INSTITUTE (BUILDING 77 / 5TH FLOOR) -- CENTURY TO ADD AND RELOCATE OFF THE EXISTING FIRE SPRINKLER PER NFPA 13 2022.
2026-07-23
BP-202602932 · FIRE · PENDING
PIEDMONT ATL LINAC 1 RENO - FP -- CFP is to add and relocate sprinklers off of existing wet system to meet NFPA 13 requirements
2026-07-22
BE-202604974 · ELECTRICAL · ISSUED
Piedmont Atlanta Hospital- Legacy OR and Organ Preservation -- Low-Voltage Data Cabling
2026-07-22
BP-202602927 · FIRE · PENDING
PIEDMONT ATLANTA HOSPITAL PRE POST -- ADVANTAGE FIRE IS TO ADD/RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM IN ACCORDANCE TO NFPA 13 2022
2026-07-22
26TMP-047563 · FIRE · OTHER
PIEDMONT ATLANTA HOSPITAL PRE POST -- ADVANTAGE FIRE IS TO ADD/RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM IN ACCORDANCE TO NFPA 13 2022
2026-07-20
BM-202603345 · HVAC · ISSUED
Piedmont Atlanta Hospital - Respiratory Therapy -- INTERIOR MODIFICATION OF EXISTING TENANT SUITE FOR NEW RESPIRATORY THERAPY STAFF OFFICES, CONFERENCE ROOM, BREAK ROOM, LOCKER ROOM, AND EQUIPMENT CLEANING AND STORAGE. The mechanical scope entails the installation of 12 air terminal units along with associated duct and piping. There is also 1 restroom fan.
2026-07-20
BM-202603343 · HVAC · PENDING
Piedmont Transplant Clinic Build-Out 5th Floor -- Interior mechanical renovation of the 5th floor of Piedmont Hospital's transplant institute. Addition of 12 reheat air terminal units along with associated ductwork and hot water piping
2026-07-16
BM-202603294 · HVAC · ISSUED
Piedmont Atlanta Hospital: Project 158- Legacy OR and Organ Preservation -- Renovation of an existing space into 2 operating rooms and a supporting sterile storage space. As BKI Mechanical, we are responsible for the HVAC scope, highlighted by a batch of VAVs, and new AHU, and associated piping
2026-07-16
BP-202602869 · FIRE · PENDING
650007-PAH Piedmont 5th Floor -- add and relocate; 152 total heads; BB-202601760
2026-07-15
BP-202602838 · PLUMBING · ISSUED
Piedmont Atlanta Hospital Proj. 158 5th Floor -- Patient Unit Fit Out on Level 5
2026-07-15
BP-202602840 · PLUMBING · ISSUED
Piedmont Atlanta Hospital Project 158 10th Floor -- Patient Fit Out on Level 10
2026-07-15
BP-202602837 · PLUMBING · ISSUED
Piedmont Atlanta Hospital Proj. 158 4th Floor -- Patient Unit Fit Out on Level 4
2026-07-02
BP-202602670 · FIRE · ISSUED
PAH LEGACY OR & ORGAN PRESERVATION -- ADVANTAGE FIRE IS TO ADD/RELOCATE OFF THE EXISTING FIRE SPRINKLER SYSTEM IN ACCORDANCE TO NFPA 13 2022.
2026-07-01
BP-202602662 · FIRE · ISSUED
650007-PAH PIEDMONT 10TH FLOOR -- DEMO SYSTEM AFTER FLOOR CONTROL VALVE AND INSTALL NEW MAIN, BRANCHLINES AND SPRINKLERS THROUGHOUT THE 10TH FLOOR. BB-202601837.