2026-10-22
Property Maintenance -- ***Apt 515*** mold, leaks, malfunctioning HVAC, plumbing issues,
2026-10-21
Property Maintenance -- ***APT 1236*** Interior damage - unfinished maintenance work and potential health and safety concerns.
2026-10-12
Property Maintenance -- exposed pipes, holes in ceiling - APT 908
2026-09-28
MAA Gardens repipe, building 1200 -- MAA Gardens Repipe Building 1200. Replace the water lines for all units in the building, 40 units in total. These units are in a stack on top of each other with the same floor plan. We are replacing only the CPVC sections with Pex A. Part of the sections have already been replaced with Pex B and we are going to be connecting there all the way to each fixture. The same holes and paths will be used for the new piping.
Professionals on this permit TOP FLIGHT PLUMBING LLC (General contractor)
2026-09-04
MAA Gardens repipe, building 900 -- MAA Gardens Repipe Building 900. Replace the water lines for all units in the building, 24 units in total. These units are in a stack on top of each other with the same floor plan. We are replacing only the CPVC sections with Pex A. Part of the sections have already been replaced with Pex B and we are going to be connecting there all the way to each fixture. The same holes and paths will be used for the new piping.
Professionals on this permit TOP FLIGHT PLUMBING LLC (General contractor)
Status changes we observed PENDING (September 4, 2026) → ISSUED (September 8, 2026)
2026-08-18
MAA Gardens repipe, building 500 -- MAA Gardens Repipe Building 500. Replace the water lines for all units in the building, 24 units in total. These units are in a stack on top of each other with the same floor plan. We are replacing only the CPVC sections with Pex A. Part of the sections have already been replaced with Pex B and we are going to be connecting there all the way to each fixture. The same holes and paths will be used for the new piping.
Professionals on this permit TOP FLIGHT PLUMBING LLC (General contractor)
Status changes we observed PENDING (August 18, 2026) → ISSUED (August 19, 2026)
2026-08-04
MAA Gardens repipe, building 700 -- MAA Gardens Repipe Building 700. Replace the water lines for all units in the building, 24 units in total. These units are in a stack on top of each other with the same floor plan. We are replacing only the CPVC sections with Pex A. Part of the sections have already been replaced with Pex B and we are going to be connecting there all the way to each fixture. The same holes and paths will be used for the new piping.
Professionals on this permit TOP FLIGHT PLUMBING LLC (General contractor)
2026-07-28
Highly Hazardous -- interior leak in bathroom ceiling - Unit 302 / CLBurdin
2026-07-23
MAA Gardens repipe, building 400 -- MAA Gardens Repipe Building 400. Replace the water lines for all units in the building, 24 units in total. These units are in a stack on top of each other with the same floor plan. We are replacing only the CPVC sections with Pex A. Part of the sections have already been replaced with Pex B and we are going to be connecting there all the way to each fixture. The same holes and paths will be used for the new piping.
Professionals on this permit TOP FLIGHT PLUMBING LLC (General contractor)
Status changes we observed PENDING (July 23, 2026) → ISSUED (July 24, 2026)
2026-07-10
Highly Hazardous -- mold in home in the bathroom and washer room when she advised her leasing agents of this issue they ignored her then eventually began to remove the walls to fix the walls are starting to turn black again she now has a open wall in her shower and its starting to leak from up there. Unit 1103. CS