2026-10-10
EPN2026-02867
· Site/Building Plans (complete project plans) · Received
Interior electrical tenant build-out of existing warehouse space: new 277/480V and 120/208V distribution including 250A MDP, 200A Panel LA, 200A Panel P01, 75KVA transformer; 147 new LED high-bay fixtures with lighting controls; receptacles and power for production lines; emergency lighting with 2000VA inverter. No new utility service, no structural work, no land disturbance. UL certification documentation for the new fixtures and electrical equipment will be provided supplementally at a later stage, prior to final inspection.
Construction Type Remodel
Total Square Feet 119461
Status changes we observed PENDING (October 10, 2026) → Received (October 10, 2026)