2026-10-16
EPN2026-02929
· Site/Building Plans (complete project plans) · Received
KAISER PERMANENTE - COMPREHENSIVE MEDICAL CENTER APC EXPANSION
INTERIOR FINISH
Status changes we observed PENDING (October 16, 2026) → Received (October 16, 2026)
2026-10-01
EPN2026-02776
· Site/Building Plans (complete project plans) · IN_PROGRESS
KAISER PERMANENTE - COMPREHENSIVE MEDICAL CENTER AUC EXPANSION
Construction Type Remodel
Total Square Feet 1031
Status changes we observed PENDING (October 1, 2026) → Received (October 1, 2026) → IN_PROGRESS (October 2, 2026)
2026-08-26
EPN2026-02448
· Site/Building Plans (complete project plans) · IN_PROGRESS
KAISER PERMANENTE - COMPREHENSIVE MEDICAL CENTER APC EXPANSION
Construction Type Remodel
Total Square Feet 1031
Status changes we observed PENDING (August 26, 2026) → Received (August 26, 2026) → CLOSED (August 27, 2026) → IN_PROGRESS (August 28, 2026)
2026-08-11
EPN2026-02278
· Site/Building Plans (complete project plans) · IN_PROGRESS
KAISER PERMANENTE - COMPREHENSIVE MEDICAL CENTER APC EXPANSION
Construction Type Remodel
Total Square Feet 3455
Status changes we observed PENDING (August 11, 2026) → Received (August 11, 2026) → IN_PROGRESS (August 12, 2026)