2026-10-22
MESCHER ELECTRICAL -- 1. Service Meter Replacement
• Disconnect and safely remove the existing service meter.
• Install a new utility-approved meter base (matching local utility requirements).
• Coordinate with the utility company for meter set / re-energization.
• Ensure proper grounding and bonding per current NEC and local code.
2. New Service Mast Installation
• Remove the existing mast (if required).
• Install a new rigid conduit mast of appropriate size and height to meet clearance requirements.
• Install new weatherhead, guy support (if needed), and proper sealing.
• Reconnect service conductors from the weatherhead to the meter base with new approved conductors as needed.
3. Install New Outdoor Sub-Panel for Pool
• Install a new outdoor-rated sub-panel in a location next to the meter.
• Install new feeder conductors from the main service panel (or meter) to the new sub-panel.
• Install weatherproof enclosure, conduit, and any required disconnects.
4. Feeder Replacement
Scope Code R1 Single Family Residence
Total Square Footage 1
Professionals on this permit CAELUM HEATING AND AIR CONDITIONING (General contractor)
2026-10-20
MESCHER ELECTRICAL -- 1. Service Meter Replacement
• Disconnect and safely remove the existing service meter.
• Install a new utility-approved meter base (matching local utility requirements).
• Coordinate with the utility company for meter set / re-energization.
• Ensure proper grounding and bonding per current NEC and local code.
2. New Service Mast Installation
• Remove the existing mast (if required).
• Install a new rigid conduit mast of appropriate size and height to meet clearance requirements.
• Install new weatherhead, guy support (if needed), and proper sealing.
• Reconnect service conductors from the weatherhead to the meter base with new approved conductors as needed.
3. Install New Outdoor Sub-Panel for Pool
• Install a new outdoor-rated sub-panel in a location next to the meter.
• Install new feeder conductors from the main service panel (or meter) to the new sub-panel.
• Install weatherproof enclosure, conduit, and any required disconnects.
4. Feeder Replacement
2026-09-03
PLANS ON LIST