2026-09-10
EPN2026-02586
· Site/Building Plans (complete project plans) · IN_PROGRESS
HUSSEY GAY BELL
Construction Type Remodel
Total Square Feet 8080
Status changes we observed PENDING (September 10, 2026) → Received (September 10, 2026) → IN_PROGRESS (September 11, 2026)
2026-09-09
EPN2026-02580
· Site/Building Plans (complete project plans) · IN_PROGRESS
NEURO SPINE
Construction Type Remodel
Total Square Feet 5280
Status changes we observed PENDING (September 10, 2026) → Received (September 10, 2026) → IN_PROGRESS (September 10, 2026)