2026-09-17
Stop Work Case -- Complaint received that an electrical inverter has been installed in an interior space without a permit and inspections and does not meet safety requirements; including but not limited to • Equipment clearances around, above, below, and between the inverters
• Electrical equipment installed directly beneath the inverters
• Wiring methods, fittings, conductor support, and routing
• Conductor bend radius and mechanical support
• Mounting conditions
• Grounding and bonding
• Panel configuration and associated electrical equipment
Zoning 1 R-5
Status changes we observed PENDING (September 17, 2026) → IN_PROGRESS (September 21, 2026)
2026-08-12
NO OTHER DOCS FOUND EXCEPT ELECTRICAL
Certificate of Occupancy No
Status changes we observed PENDING (August 12, 2026) → CLOSED (August 13, 2026)