2026-10-19
EPN2026-02941
· Site/Building Plans (complete project plans) · PENDING
door ways added between 720 &730
Construction Type Remodel
Total Square Feet 4991
2026-08-28
EPN2026-02468
· Site/Building Plans (complete project plans) · IN_PROGRESS
SPEC SUITE
Construction Type Remodel
Total Square Feet 1938
Status changes we observed PENDING (August 28, 2026) → Received (August 28, 2026) → IN_PROGRESS (August 31, 2026)
2026-08-28
EPN2026-02469
· Site/Building Plans (complete project plans) · IN_PROGRESS
FINE ART HOUSE
Construction Type Remodel
Total Square Feet 1502
Status changes we observed PENDING (August 28, 2026) → Received (August 28, 2026) → IN_PROGRESS (August 31, 2026)
2026-08-28
EPN2026-02470
· Site/Building Plans (complete project plans) · IN_PROGRESS
SPEC SUITE
Construction Type Remodel
Total Square Feet 4455
Status changes we observed PENDING (August 28, 2026) → Received (August 28, 2026) → IN_PROGRESS (August 31, 2026)
2026-08-26
EPN2026-02454
· Site/Building Plans (complete project plans) · IN_PROGRESS
CLEARLINE
Construction Type Remodel
Total Square Feet 3853
Status changes we observed PENDING (August 26, 2026) → Received (August 26, 2026) → IN_PROGRESS (August 27, 2026)
2026-07-22
EPN2026-02060
· Site/Building Plans (complete project plans) · PENDING
House panel install and power approval.
Construction Type Remodel
Initial Lot/Unit Count 400
Status changes we observed PENDING (August 5, 2026) → Pending Documents (August 5, 2026)
2026-07-02
EPN2026-01866
· Site/Building Plans (complete project plans) · PENDING
INTERIOR FINISH, STE 180 (REF TNC2026-01572 CHANGE IN FLOOR PLAN)
Construction Type Remodel
Total Square Feet 1770
Status changes we observed PENDING (August 5, 2026) → Pending Resubmittal (August 5, 2026)