2026-10-08
Water Resources Administrative Variance
Status changes we observed PENDING (October 8, 2026) → Received (October 8, 2026) → PENDING (October 9, 2026)
2026-10-07
EPN2026-02844
· Site/Building Plans (complete project plans) · CLOSED
No description on file.
Construction Type New
Total Square Feet 202293
Initial Lot/Unit Count 13
Status changes we observed PENDING (October 7, 2026) → Received (October 7, 2026) → CLOSED (October 8, 2026)
2026-08-14
EPN2026-02312
· Site/Building Plans (complete project plans) · IN_PROGRESS
TWIN FORKS
Construction Type New
Total Square Feet 218671
Initial Lot/Unit Count 13
Status changes we observed PENDING (August 14, 2026) → Received (August 14, 2026) → IN_PROGRESS (August 14, 2026)