2026-10-09
EPN2026-02865
· Site/Building Plans (complete project plans) · Received
Existing areas of approximately 15,380 sq. ft. to be converted to office spaces.
Construction Type Remodel
Status changes we observed PENDING (October 9, 2026) → Received (October 9, 2026)
2026-08-20
EPN2026-02384
· Site/Building Plans (complete project plans) · CLOSED
No description on file.
Construction Type New
Total Square Feet 0
Status changes we observed PENDING (August 20, 2026) → Received (August 20, 2026) → PENDING (August 21, 2026) → CLOSED (August 25, 2026)
2026-08-17
EPN2026-02337
· Site/Building Plans (complete project plans) · Closed
Electrical lighting
Construction Type Remodel
Total Square Feet 3044
Status changes we observed CLOSED (August 17, 2026) → Closed (August 17, 2026)
2026-07-22
EPN2026-02054
· Site/Building Plans (complete project plans) · PENDING
INTERIOR FINISH, LIGHTERA- PHASE 3
Construction Type Remodel
Total Square Feet 52520
Status changes we observed PENDING (August 5, 2026) → Pending Resubmittal (August 5, 2026)