2026-09-24
EPN2026-02725
· Site/Building Plans (complete project plans) · Plan Review In Progress
INTERIOR FINISH, STE410
Construction Type Remodel
Total Square Feet 11809
Status changes we observed IN_PROGRESS (September 25, 2026) → Plan Review In Progress (September 25, 2026)
2026-09-04
EPN2026-02544
· Site/Building Plans (complete project plans) · IN_PROGRESS
COURTYARD BY MARRIOT - RETAINING WALL
Construction Type Remodel
Total Square Feet 2130
Status changes we observed PENDING (September 4, 2026) → Received (September 4, 2026) → IN_PROGRESS (September 8, 2026)
2026-09-03
EPN2026-02525
· Site/Building Plans (complete project plans) · IN_PROGRESS
SUGARLOAF TERRACE - GROUND LEVEL (PATIO IMPROVEMENTS)
Construction Type Remodel
Total Square Feet 2130
Status changes we observed PENDING (September 3, 2026) → Received (September 3, 2026) → IN_PROGRESS (September 8, 2026)
2026-08-21
EPN2026-02397
· Site/Building Plans (complete project plans) · IN_PROGRESS
SUGARLOAF TERRACE - BLDG AMENITY IMPROVEMENTS
Total Square Feet 103223
Status changes we observed PENDING (August 21, 2026) → Received (August 21, 2026) → IN_PROGRESS (August 24, 2026)
2026-08-13
EPN2026-02308
· Site/Building Plans (complete project plans) · IN_PROGRESS
PPG DULUTH - FACADE UPDATE
Construction Type Remodel
Status changes we observed PENDING (August 13, 2026) → Received (August 13, 2026) → IN_PROGRESS (August 14, 2026)
2026-08-03
26TMP-076748
· Building (any single-family structure) · OTHER
sugarloaf