2026-07-14
Building 1, Level 2 underground -- Building 1 Level 2 - New plumbing install for underground - retail
2026-07-14
Building 2, Basement Units -- Building 2 Basement, New plumbing install, 10 units
2026-07-08
Bldg 1 Retail 6 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 2 Retail 3 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Retail 7 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 2 Parking Deck Temp Power -- temp power for new apartment complex parking deck
2026-07-08
Bldg 1 Retail 5 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Retail 1 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Parking Deck Temp Power -- temp power for new apartment complex parking deck
2026-07-08
Bldg 2 Retail 2 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Retail 4 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Retail 2 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 2 Retail 1 Temp Power -- Temp power for new apartment complex retail space
2026-07-08
Bldg 1 Retail 3 Temp Power -- Temp power for new apartment complex retail space
2026-07-07
Bldg 1, 2nd Floor -- install new electrical for new apartments
2026-07-07
Bldg 1, Retail 3 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, Basement -- install new electrical for new apartments and common areas
2026-07-07
Bldg 2, retail 3 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, 4th Floor -- install new electrical for new apartments and common areas
2026-07-07
Bldg 1, Retail 5 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, 3rd Floor -- install new electrical for new apartments and common areas
2026-07-07
Bldg 1, Retail 6 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, Retail 1 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 1, Retail 2 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 1, 6th floor -- install new electrical for new apartments
2026-07-07
Bldg 1, 3rd Floor -- install new electrical for new apartments
2026-07-07
Bldg 1, 4th floor -- install new electrical for new apartments
2026-07-07
Bldg 2, 1st Floor -- install new electrical for new apartments and common areas
2026-07-07
Bldg 1, Retail 1 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 1, Retail 4 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 1, 5th Floor -- install new electrical for new apartments
2026-07-07
Bldg 2 Basement -- temp power for new multifamily construction
2026-07-07
Bldg 2, 1st Floor Temp Power -- temp power for new multifamily construction
2026-07-07
Bldg 2, 2nd Floor -- install new electrical for new apartments and common areas
2026-07-07
Bldg 1, Retail 7 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, Retail 2 -- install new electrical in new retail space of multifamily apartment complex
2026-07-07
Bldg 2, Parking Deck -- install new electrical for new apartment complex parking deck
2026-07-07
Bldg 2, 5th Floor -- install new electrical for new apartments and common areas
2026-07-07
Bldg 1, Parking Deck -- install new electrical for new apartment complex parking deck
2026-07-06
Bldg 1, 1st Floor -- Install new electrical for new apartments and amenity spaces
THIS PERMIT HAS 5 SERIVCES 2-1600 AMP, 1-2000 AMP 1-600 AMP , 1-200 AMP AND 24 FEEDERS (125 AMPS)