2026-09-18
· DEMOLITION OF EXISTING SURFACES FOR THE INSTALLATION OF EV CHARGERS.
· GRADING OF SURFACES ASSOCIATED WITH EVSE TO COMPLY WITH ADA REQUIREMENTS.
· CONVERTING (10) STANDARD PARKING STALLS TO (7) STANDARD EV PARKING STALLS AND (1) VAN
ACCESSIBLE EV PARKING STALL.
· INSTALL (1) UTILITY TRANSFORMER TO BE COORDINATED WITH TECO.
· INSTALL (1) LOW VOLTAGE SWITCHBOARD ASSEMBLY.
· INSTALL (4) 350KW DELTA POWER CABINETS.
· INSTALL (4) 350KW DELTA EV CHARGING DISPENSERS.
· INSTALL (24) PIPE BOLLARDS.