2026-09-04
Debonair _MISC (RES)(PLT) -- New driveway and walkway concrete will be installed.
Reported project value $13,146
Scope Code New Residential Driveway
Application Square Footage 1160
Professionals on this permit EXEMPT 26-PEOP-02185 (General contractor)
2026-09-02
No description on file.
2026-09-01
Driveway and walkway replacement (RES) -- New driveway and walkway concrete will be installed.
Reported project value $13,146
Scope Code R1 Single Family Residence
Application Square Footage 1160
2026-08-25
Driveway and walkway replacement -- Solid Concrete Solutions LLC will provide all labor, equipment, materials, demolition, hauling, concrete placement, finishing, and cleanup necessary to complete the following work.
Project Areas
• Driveway: 92' × 10' — approximately 920 sq. ft.
• Walkway: 20' × 4' — approximately 80 sq. ft., to be removed and replaced with concrete.
• Walkway: 40' × 4' — approximately 160 sq. ft., to be removed and replaced with grass.
• Total new concrete area: Approximately 1,000 sq. ft.
Concrete Specifications
• New driveway and walkway concrete will be installed at approximately 4 inches thick.
• Concrete mix will be 3,500 PSI.
• Concrete will be placed using a concrete pump and professionally finished.
Project Schedule – Approximately 3 Days
Day 1 – Demolition & Preparation
• Demolish and remove the existing 92' × 10' driveway.
• Demolish and remove the existing 20' × 4' walkway.
• Demolish and remove the existing 40' × 4' walkway that will be converted to grass.
• Load, haul away, and properly dispose of demolished concrete and debris.
• Prepare the work area and set forms for the new driveway and walkway.
• Prepare the 40' × 4' area for restoration with grass.
Day 2 – Concrete Placement & Finishing
• Place approximately 4 inches of 3,500 PSI concrete for the driveway and 20' × 4' walkway.
• Concrete will be placed with the use of a pump.
• Concrete will be leveled and professionally finished.
Day 3 – Final Cleanup
• Remove all concrete forms.
• Clean the surrounding work areas.
• Remove remaining construction debris.
• Perform a final jobsite cleanup and inspection.
Estimated Project Duration: 3 working days, subject to weather conditions, site conditions, and concrete availability.
2026-07-13
1621 Kenmore St -- Get temporary power in the house
Professionals on this permit ACR BRIGHT ELECTRIC LLC (General contractor)