DescriptionCRIM HS GYMNASIUM ROOF REPLACEMENT (COM) (CC) -- SECTION 01 11 00 – SUMMARY OF WORK 1. Project Name: Crim High School Gymnasium Roof Replacement. 2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW. 3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317. 4. Project consists of the complete removal and replacement of the steep-slope asphalt shingle roofing system on the gymnasium building, including full Roof Deck replacement in kind, sheet metal flashings, and box gutter and downspout system, as specified herein. B. Scope of Work 1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all roofing accessories down to the structural Roof Deck. Remove all existing gutters, downspouts, and flashings. 2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace in kind, matching existing material, thickness, grade, span rating, and attachment method, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck Replacement. 3. New Roofing System: Furnish and install a complete new steep-slope asphalt shingle roofing system including high-temperature ice and water protection membrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 Class H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer to Section 07 31 13 – Asphalt Shingles. 4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. Refer to Section 07 60 00 – Flashing and Sheet Metal. 5. Gutters and Downspouts: Remove and replace existing box gutter and downspout system with new box 24 gauge galvanized steel gutters and downspouts with conductor heads. Refer to Section 22 12 00 – Gutters and Downspouts. 6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch. 7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave vents, or other ventilation openings shall be installed. C. Work Not Included 1. Interior work below the Roof Deck. 2. Structural Framing Repairs. 3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract Drawings. D. Related Documents 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00. E. Work Sequence and Coordination 1. Coordinate with Owner and School Administration to minimize disruption. The gymnasium may be in use during construction; refer to Section 00 73 00 – Special Conditions – Occupied School Facilities. 2. Provide continuous temporary protection of the building interior at all times during roofing operations. Do not leave the structural framing or new Roof Deck exposed to weather overnight without temporary waterproofing in place. 3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that the building remains watertight at all times.
Estimated value$542,900
Original filingView on city site →

Property

Address256 CLIFTON ST SE, Atlanta 30317
Parcel ID15 178 01 001

Contractor

GeneralRoof Technology Partners, LLC (Ryan Jacob Gaddy)
Phone📞 678-401-5200

History (4 captures)

List update 2026-07-15 04:06:42.218223+00:00
Status: PENDING
First captured -- nothing to compare against yet.
Detail fetch 2026-07-15 04:29:49.552894+00:00
Status: PENDING
address: 256 CLIFTON ST SE, ATLANTA GA 30317None
date_filed: 2026-07-14None
description: SECTION 01 11 00 – SUMMARY OF WORK 1. Project Name: Crim High School Gymnasium Roof Replacement. 2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW. 3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317. 4. Project consists of the complete removal and replacement of the steep-slope asphalt shingle roofing system on the gymnasium building, including full Roof Deck replacement in kind, sheet metal flashings, and box gutter and downspout system, as specified herein. B. Scope of Work 1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all roofing accessories down to the structural Roof Deck. Remove all existing gutters, downspouts, and flashings. 2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace in kind, matching existing material, thickness, grade, span rating, and attachment method, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck Replacement. 3. New Roofing System: Furnish and install a complete new steep-slope asphalt shingle roofing system including high-temperature ice and water protection membrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 Class H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer to Section 07 31 13 – Asphalt Shingles. 4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. Refer to Section 07 60 00 – Flashing and Sheet Metal. 5. Gutters and Downspouts: Remove and replace existing box gutter and downspout system with new box 24 gauge galvanized steel gutters and downspouts with conductor heads. Refer to Section 22 12 00 – Gutters and Downspouts. 6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch. 7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave vents, or other ventilation openings shall be installed. C. Work Not Included 1. Interior work below the Roof Deck. 2. Structural Framing Repairs. 3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract Drawings. D. Related Documents 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00. E. Work Sequence and Coordination 1. Coordinate with Owner and School Administration to minimize disruption. The gymnasium may be in use during construction; refer to Section 00 73 00 – Special Conditions – Occupied School Facilities. 2. Provide continuous temporary protection of the building interior at all times during roofing operations. Do not leave the structural framing or new Roof Deck exposed to weather overnight without temporary waterproofing in place. 3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that the building remains watertight at all times.None
detail_fields: {'Owner': 'ATLANTA BOARD OF EDUCATION\n*', 'Project Description': 'CRIM HS GYMNASIUM ROOF REPLACEMENT\nSECTION 01 11 00 – SUMMARY OF WORK\n1. Project Name: Crim High School Gymnasium Roof Replacement.\n2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW.\n3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317.\n4. Project consists of the complete removal and replacement of the steep-slope \nasphalt shingle roofing system on the gymnasium building, including full Roof \nDeck replacement in kind, sheet metal flashings, and box gutter and downspout \nsystem, as specified herein.\nB. Scope of Work\n1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all \nroofing accessories down to the structural Roof Deck. Remove all existing \ngutters, downspouts, and flashings.\n2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace \nin kind, matching existing material, thickness, grade, span rating, and attachment \nmethod, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck \nReplacement.\n3. New Roofing System: Furnish and install a complete new steep-slope asphalt \nshingle roofing system including high-temperature ice and water protection \nmembrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 \nClass H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer \nto Section 07 31 13 – Asphalt Shingles.\n4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. \nRefer to Section 07 60 00 – Flashing and Sheet Metal.\n5. Gutters and Downspouts: Remove and replace existing box gutter and \ndownspout system with new box 24 gauge galvanized steel gutters and \ndownspouts with conductor heads. Refer to Section 22 12 00 – Gutters and \nDownspouts.\n6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch.\n7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave \nvents, or other ventilation openings shall be installed.\nC. Work Not Included\n1. Interior work below the Roof Deck.\n2. Structural Framing Repairs.\n3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract \nDrawings.\nD. Related Documents\n1. Drawings and general provisions of the Contract, including General and \nSupplementary Conditions, apply to this Section.\n2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00.\nE. Work Sequence and Coordination\n1. Coordinate with Owner and School Administration to minimize disruption. The \ngymnasium may be in use during construction; refer to Section 00 73 00 – \nSpecial Conditions – Occupied School Facilities.\n2. Provide continuous temporary protection of the building interior at all times during \nroofing operations. Do not leave the structural framing or new Roof Deck \nexposed to weather overnight without temporary waterproofing in place.\n3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that \nthe building remains watertight at all times.', 'Licensed Professional': 'Ryan Jacob Gaddy\nRoof Technology Partners, LLC\nOCCTX26-15283\n3232 Bell Park Drive\nWoodstock, GA, 30188\nUnited States\nHome Phone:\n678-401-5200\nGEN CONT GCQA009303'} (new field)
detail_url: https://aca-prod.accela.com/ATLANTA_GA/Cap/CapDetail.aspx?Module=Building&TabName=Building&capID1=26CAP&capID2=00000&capID3=00ERW&agencyCode=ATLANTA_GA&IsToShowInspection=None
parcel_number: 15 178 01 001 (new field)
project_name: CRIM HS GYMNASIUM ROOF REPLACEMENTNone
record_number: BB-202606134None
record_type: Commercial AlterationNone
status: ACA PendingNone
List update 2026-07-19 19:07:55.709670+00:00
Status: PENDING
address: 256 CLIFTON ST SE, ATLANTA GA 30317 (new field)
date_filed: 2026-07-14 (new field)
description: SECTION 01 11 00 – SUMMARY OF WORK 1. Project Name: Crim High School Gymnasium Roof Replacement. 2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW. 3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317. 4. Project consists of the complete removal and replacement of the steep-slope asphalt shingle roofing system on the gymnasium building, including full Roof Deck replacement in kind, sheet metal flashings, and box gutter and downspout system, as specified herein. B. Scope of Work 1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all roofing accessories down to the structural Roof Deck. Remove all existing gutters, downspouts, and flashings. 2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace in kind, matching existing material, thickness, grade, span rating, and attachment method, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck Replacement. 3. New Roofing System: Furnish and install a complete new steep-slope asphalt shingle roofing system including high-temperature ice and water protection membrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 Class H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer to Section 07 31 13 – Asphalt Shingles. 4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. Refer to Section 07 60 00 – Flashing and Sheet Metal. 5. Gutters and Downspouts: Remove and replace existing box gutter and downspout system with new box 24 gauge galvanized steel gutters and downspouts with conductor heads. Refer to Section 22 12 00 – Gutters and Downspouts. 6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch. 7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave vents, or other ventilation openings shall be installed. C. Work Not Included 1. Interior work below the Roof Deck. 2. Structural Framing Repairs. 3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract Drawings. D. Related Documents 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00. E. Work Sequence and Coordination 1. Coordinate with Owner and School Administration to minimize disruption. The gymnasium may be in use during construction; refer to Section 00 73 00 – Special Conditions – Occupied School Facilities. 2. Provide continuous temporary protection of the building interior at all times during roofing operations. Do not leave the structural framing or new Roof Deck exposed to weather overnight without temporary waterproofing in place. 3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that the building remains watertight at all times. (new field)
detail_fields: {'Owner': 'ATLANTA BOARD OF EDUCATION\n*', 'Project Description': 'CRIM HS GYMNASIUM ROOF REPLACEMENT\nSECTION 01 11 00 – SUMMARY OF WORK\n1. Project Name: Crim High School Gymnasium Roof Replacement.\n2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW.\n3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317.\n4. Project consists of the complete removal and replacement of the steep-slope \nasphalt shingle roofing system on the gymnasium building, including full Roof \nDeck replacement in kind, sheet metal flashings, and box gutter and downspout \nsystem, as specified herein.\nB. Scope of Work\n1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all \nroofing accessories down to the structural Roof Deck. Remove all existing \ngutters, downspouts, and flashings.\n2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace \nin kind, matching existing material, thickness, grade, span rating, and attachment \nmethod, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck \nReplacement.\n3. New Roofing System: Furnish and install a complete new steep-slope asphalt \nshingle roofing system including high-temperature ice and water protection \nmembrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 \nClass H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer \nto Section 07 31 13 – Asphalt Shingles.\n4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. \nRefer to Section 07 60 00 – Flashing and Sheet Metal.\n5. Gutters and Downspouts: Remove and replace existing box gutter and \ndownspout system with new box 24 gauge galvanized steel gutters and \ndownspouts with conductor heads. Refer to Section 22 12 00 – Gutters and \nDownspouts.\n6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch.\n7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave \nvents, or other ventilation openings shall be installed.\nC. Work Not Included\n1. Interior work below the Roof Deck.\n2. Structural Framing Repairs.\n3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract \nDrawings.\nD. Related Documents\n1. Drawings and general provisions of the Contract, including General and \nSupplementary Conditions, apply to this Section.\n2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00.\nE. Work Sequence and Coordination\n1. Coordinate with Owner and School Administration to minimize disruption. The \ngymnasium may be in use during construction; refer to Section 00 73 00 – \nSpecial Conditions – Occupied School Facilities.\n2. Provide continuous temporary protection of the building interior at all times during \nroofing operations. Do not leave the structural framing or new Roof Deck \nexposed to weather overnight without temporary waterproofing in place.\n3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that \nthe building remains watertight at all times.', 'Licensed Professional': 'Ryan Jacob Gaddy\nRoof Technology Partners, LLC\nOCCTX26-15283\n3232 Bell Park Drive\nWoodstock, GA, 30188\nUnited States\nHome Phone:\n678-401-5200\nGEN CONT GCQA009303'}None
detail_url: https://aca-prod.accela.com/ATLANTA_GA/Cap/CapDetail.aspx?Module=Building&TabName=Building&capID1=26CAP&capID2=00000&capID3=00ERW&agencyCode=ATLANTA_GA&IsToShowInspection= (new field)
parcel_number: 15 178 01 001None
project_name: CRIM HS GYMNASIUM ROOF REPLACEMENT (COM) (CC) (new field)
record_number: BB-202606134 (new field)
record_type: Commercial Alteration (new field)
status: Accepted (new field)
List update 2026-07-20 16:17:19.398412+00:00
Status: PENDING
status: AcceptedRouted for Review
View full history & open as full page ↗