address:
256 CLIFTON ST SE, ATLANTA GA 30317 (new field)
date_filed:
2026-07-14 (new field)
description:
SECTION 01 11 00 – SUMMARY OF WORK
1. Project Name: Crim High School Gymnasium Roof Replacement.
2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW.
3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317.
4. Project consists of the complete removal and replacement of the steep-slope
asphalt shingle roofing system on the gymnasium building, including full Roof
Deck replacement in kind, sheet metal flashings, and box gutter and downspout
system, as specified herein.
B. Scope of Work
1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all
roofing accessories down to the structural Roof Deck. Remove all existing
gutters, downspouts, and flashings.
2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace
in kind, matching existing material, thickness, grade, span rating, and attachment
method, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck
Replacement.
3. New Roofing System: Furnish and install a complete new steep-slope asphalt
shingle roofing system including high-temperature ice and water protection
membrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158
Class H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer
to Section 07 31 13 – Asphalt Shingles.
4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings.
Refer to Section 07 60 00 – Flashing and Sheet Metal.
5. Gutters and Downspouts: Remove and replace existing box gutter and
downspout system with new box 24 gauge galvanized steel gutters and
downspouts with conductor heads. Refer to Section 22 12 00 – Gutters and
Downspouts.
6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch.
7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave
vents, or other ventilation openings shall be installed.
C. Work Not Included
1. Interior work below the Roof Deck.
2. Structural Framing Repairs.
3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract
Drawings.
D. Related Documents
1. Drawings and general provisions of the Contract, including General and
Supplementary Conditions, apply to this Section.
2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00.
E. Work Sequence and Coordination
1. Coordinate with Owner and School Administration to minimize disruption. The
gymnasium may be in use during construction; refer to Section 00 73 00 –
Special Conditions – Occupied School Facilities.
2. Provide continuous temporary protection of the building interior at all times during
roofing operations. Do not leave the structural framing or new Roof Deck
exposed to weather overnight without temporary waterproofing in place.
3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that
the building remains watertight at all times. (new field)
detail_fields:
{'Owner': 'ATLANTA BOARD OF EDUCATION\n*', 'Project Description': 'CRIM HS GYMNASIUM ROOF REPLACEMENT\nSECTION 01 11 00 – SUMMARY OF WORK\n1. Project Name: Crim High School Gymnasium Roof Replacement.\n2. Owner: Atlanta Public Schools (APS). APS Project No. 26-100325-Q-AW.\n3. Project Location: 256 Clifton Street NE, Atlanta, GA 30317.\n4. Project consists of the complete removal and replacement of the steep-slope \nasphalt shingle roofing system on the gymnasium building, including full Roof \nDeck replacement in kind, sheet metal flashings, and box gutter and downspout \nsystem, as specified herein.\nB. Scope of Work\n1. Roof Tear-Off: Remove existing asphalt shingles, synthetic underlayment, and all \nroofing accessories down to the structural Roof Deck. Remove all existing \ngutters, downspouts, and flashings.\n2. Full Roof Deck Replacement: Remove the entire existing Roof Deck and replace \nin kind, matching existing material, thickness, grade, span rating, and attachment \nmethod, over the full 13,800 SF roof area. Refer to Section 07 05 00 – Roof Deck \nReplacement.\n3. New Roofing System: Furnish and install a complete new steep-slope asphalt \nshingle roofing system including high-temperature ice and water protection \nmembrane, synthetic underlayment, architectural asphalt shingles (ASTM D7158 \nClass H, 150 mph minimum), starter strips, ridge caps, and all accessories. Refer \nto Section 07 31 13 – Asphalt Shingles.\n4. Sheet Metal Flashings: Furnish and install all associated sheet metal flashings. \nRefer to Section 07 60 00 – Flashing and Sheet Metal.\n5. Gutters and Downspouts: Remove and replace existing box gutter and \ndownspout system with new box 24 gauge galvanized steel gutters and \ndownspouts with conductor heads. Refer to Section 22 12 00 – Gutters and \nDownspouts.\n6. Total Roof Area: Approximately 13,800 SF; steep-slope, 3.5:12 pitch.\n7. The gymnasium roof is a non-vented conditioned assembly. No ridge vents, eave \nvents, or other ventilation openings shall be installed.\nC. Work Not Included\n1. Interior work below the Roof Deck.\n2. Structural Framing Repairs.\n3. HVAC, electrical, or plumbing work unless specifically indicated on the Contract \nDrawings.\nD. Related Documents\n1. Drawings and general provisions of the Contract, including General and \nSupplementary Conditions, apply to this Section.\n2. Related Sections: 07 01 50.19, 07 05 00, 07 31 13, 07 60 00, 22 12 00.\nE. Work Sequence and Coordination\n1. Coordinate with Owner and School Administration to minimize disruption. The \ngymnasium may be in use during construction; refer to Section 00 73 00 – \nSpecial Conditions – Occupied School Facilities.\n2. Provide continuous temporary protection of the building interior at all times during \nroofing operations. Do not leave the structural framing or new Roof Deck \nexposed to weather overnight without temporary waterproofing in place.\n3. Sequence tear-off, Roof Deck replacement, and new roofing installation so that \nthe building remains watertight at all times.', 'Licensed Professional': 'Ryan Jacob Gaddy\nRoof Technology Partners, LLC\nOCCTX26-15283\n3232 Bell Park Drive\nWoodstock, GA, 30188\nUnited States\nHome Phone:\n678-401-5200\nGEN CONT GCQA009303'} → None
detail_url:
https://aca-prod.accela.com/ATLANTA_GA/Cap/CapDetail.aspx?Module=Building&TabName=Building&capID1=26CAP&capID2=00000&capID3=00ERW&agencyCode=ATLANTA_GA&IsToShowInspection= (new field)
parcel_number:
15 178 01 001 → None
project_name:
CRIM HS GYMNASIUM ROOF REPLACEMENT (COM) (CC) (new field)
record_number:
BB-202606134 (new field)
record_type:
Commercial Alteration (new field)
status:
Accepted (new field)